Work continues on the Gospić cogeneration plant, which we are carrying out in cooperation with our partners from ĐĐ TEP d.o.o. The scope of work includes boiler and equipment insulation in the range of approx. 2000 m², pipeline insulation in the range of approx. 2000 m², and the supply and installation of boiler brickwork in the quantity of 15 tons. The expected completion deadline for the work is the end of December this year.
Work continues on the cogeneration plant Gospić, which we are performing in cooperation with our partners from ĐĐ TEP d.o.o. The scope of work includes insulation of the boiler and equipment over an area of 2,000 m², pipeline insulation over a length of approximately 2,000 m, and the delivery and installation of boiler walls totaling 15 tons. The projected completion date for the works is the end of December this year.