Brinje – Construction of a biomass cogeneration plant has begun

The site for the construction of the biomass cogeneration plant is located in Obadine, covering an area of 3.3 hectares. The main contractor is Đuro Đaković TEP d.o.o. The total value of the entire plant is 18 million kuna, which is also one of the largest investments in the area of the Municipality of Brinje. ĐĐ Montaža Izolak is performing insulation works for partners from TEP.

It's a plant with a power output of 5MW electrical and 10MW thermal energy. Wood chips will be used as the main raw material.

Insulation work for partners from TEP-a include

  • Boiler and equipment insulation in the scope of approx. 1800 m²
  • Insulation of pipelines on an area of approx. 2700 m²
  • Delivery and installation of boiler lining for 13 tons

On this project, we are doing the insulation work for the electrostatic precipitator and for our partners from MAGMA LLC. Požega, which includes insulation in the scope of approx. 600 m².